Project Scope
WJFE was contacted to provide the erection plans for eleven new steel girder bridges and the demolition plans for three existing steel girder bridges. Seven of the new bridges were multi-lane curved girder bridges where WJFE used finite analysis to analyze girder stability during all stages of the erection operation, temporary shoring towers, and subsurface analysis. Multiple crane locations as well as tandem pick were required to complete the erection.
Location: Queens, NY | Client: Halmar International – Northeast Structural Steel, JV | Owner: NYSDOT
Kew Gardens Main Viaduct




Project Scope
WJFE provided erection plans for two bridges, each over 225ft long, crossing the Van Wyck Expressway along with a connecting bridge ramp and the structural lifting of an existing pedestrian bridge.
Location: Queens, NY | Client: Northeast Structural Steel | Owner: NYSDOT
Penn Station Access Project (Design Build)




Project Scope
WJFE provided erection plans for four bridges (including demolition) and four train station platforms with canopies. Each erection plan had multiple stages and crane locations to complete the erection and demolition operation. Each operation also included bridge jacking, structural lifting, and shoring tower components.
Location: Bronx, NY | Client: American Structural Works | Owner: MTA
Reconstruction of Ramp OCH and Interim Repairs of 4 Bridges Spanning the Cross Bronx Expressway (I-95)




Project Scope
Northeast Structural Steel reached out to WJFE to provide the erection plans for two beam replacements inside the existing concrete cellular bridge structure. This required each beam to be installed using a crane and rigging system with a cantilevered counterweighted lifting beam.